Oryx, Jordan, 10 MW

14°

Weather Ma'an, Jordan

Flau vind, 1.5 m/s
from Nordvest

Weather forecast provided from yr.no

The Oryx project is situated 200 km south of Amman in the municipality of Maan in Jordan and is Scatec Solar’s first power plant in the Middle East.

Project key figures

  • 10 MW
  • 56 ha
  • Single-axis tracker
  • BYD polycrystalline
  • SMA
  • 2,450 kWh/kWp
  • 25, 000 MWh per annum

Ownership and PPA

PPA with NEPCO for a period of 20 years

Project owners:

Scatec Solar ASA (Norway)
Quest Energy Investment LLC

Project development

Scatec Solar developed the project and financing was secured in the fourth quarter of 2014.

Project Execution

The construction of the 10 MW power plant commenced in the first quarter of 2015. Scatec Solar has the leading role for all EPC activities and is also responsible for managing the construction phase.

Operation and maintenance

Scatec Solar will be operator of the plant through an O&M service contract.

Securing financing for the Jordanian projects was an important milestone for Scatec Solar. I am pleased to see that our approach to team up with local partners and strong finance institutions bring about such great results

Raymond Carlsen - CEO, Scatec Solar

Project highlights

First solar investment in the region

  • The Oryx project is the first solar power plant constructed by Scatec Solar in the Middle East

Socially responsible

  • CO2 reduction of 15,000 tons per annum

Project timeline

  • Mar 2014

    Power Purchase Agreement

  • Mar 2015

    Start of Construction